1.1
BCDS - Bunch
Compressor Design
Task Manager:
M. Pedrozzi (PSI)
1.1.1
Milestones
- Goal 1. Recruit a
post-doc accelerator scientist.
- Milestones
- January 05:
Advertise post doc. positions at PSI (completed).
- April 05:
Creation of a Web site for the BCDS Task (completed -http://eurotev.web.psi.ch/)
- March 05: Post
doc Recruited (Frank Schulte, DESY) (completed)
- July 05: Post
doc starting his work at PSI.
- Goal 2. Beam
specifications for Multi TeV compressor and path length tuning chicane.
- Milestones
- June 05:
Produce first set of beam specifications and performance goals for the
compressor to be discussed within ILPS.
- July 05:
Produce specifications for path length chicane (compression + phase and
energy correction)
- August 05:
Definitive specification and performance goal for simulation work
- Goal 3. Chicane,
first order conceptual designs.
- Milestones
- December 05:
Design with linear chirp and Gaussian electron distributions.
.Optimization with 1D CSR effects and with respect to ISR.
- December 05: Benchmark CSR computation with different 1D
model.
- January 06: Chicane after turn around loop design with
linear chirp and Gaussian electron distributions. Optimization with 1D
CSR effects.
- January 06: Chicane Benchmark CSR computation with
different 1D mode
- Goal 4: Chicane second order conceptual designs.
- June 06:
Compression chicane optimization with 2D and 3D CSR models.
- June 06: Path
length/compression chicane optimization with 2D and 3D CSR models
1.1.2
Following
activities
- Compression
chicane, third order conceptual design
- Compression
chicane optimization using phase space distributions from start to end
simulations (exchange between tasks).
- Path
length/compression chicane optimization
using phase space distributions from start to end simulations.
- Chicane fourth order conceptual designs
- Compression
chicane lattice design and performance study with respect to dynamic
and static imperfections (energy jitter, alignment errors).
- Turn
around lattice design.
1.1.3
Task integration
The task activities should be
integrated
and considered as an extension of the present effort made for the ILC
bunch
compressor design, mainly coordinated by SLAC
(http://www-project.slac.stanford.edu/ilc/acceldev/LET/BC/).
The multi-TeV beam parameters specifications upstream and downstream of
the
chicanes are presently driven by the CLIC requirements. The transport
studies
from the damping ring to the IP (task LAST) should give a realistic
phase space
for the ultimate chicane optimisation. The chicane simulation results
and in
particular the sensitivity to dynamic and static imperfections requires
as well
a close interaction with the LAST activities.
1.1.4
Deliverables
The
deliverables in Jan 2008 are the following.
1.
A
conceptual design of a compression chicane
suitable for multi-TeV linear colliders with an evaluation of the CSR
effects
and the compressor performances.
2.
A
conceptual design of a path length tuning
chicane including the CSR effects and the turn around loop lattice.